Tuesday, October 3: boat-support for dive work; attempted to contact brain via radio units but couldn't; climbed stick, installed rungs and removed brain to take it back to land; downloaded memory module contents; replaced and rewired brain's radio unit; wrote a new CMRC3 program to include bic re-address logic and tested it thoroughly; pulled a new cable for shallow BIC and rewired its plug at top; swapped out surface bic; reinstalled brain (but GPS cable is knocked loose); confirmed that station was NOT transmitting
Wednesday: fixed GPS cable in brain; attempted to fix broken shallow-ctd plug but doesn't work; tidied/sealed station and removed rungs (twice!).
Jim Hendee:
The station lines and chains were cleaned, the shallow CTD swapped out, and all three BICs swapped out. Station should undergo some reorganization of the cables and more intensive cleaning.
This site is for providing CMRC3 ICON/CREWS field maintenance records for NOAA/AOML/ICON data management purposes. Please update this blog whenever new operations are performed in the field, so that AOML can coordinate their efforts with the CMRC ICON/CREWS field efforts.